The composites and intermediates producer required the cleaning of a heat exchanger unit to avoid the delay of production. If the unit is left too long without a routine clean heat transfer is compromised, costing the site valuable production time. The plant, therefore, needed to ensure that the fouled unit was cleaned to a high standard to avoid unnecessary downtime that would prevent the plant from operating as usual and maximise run time in the future.
Having worked with the company for many years, we used our knowledge and experience of the client’s assets to clear the fouling within one day. Our specialised cleaning heads operate in a time-sensitive manner, clearing fouling in a single pass.
A team of three used Tube Tech’s high-pressure cleaning heads to complete the cleaning task in one shift, significantly reducing downtime for the plant.