- As no chemicals were to be used the Tube Tech team developed its very own 7mm to 8mm high-pressure micro lance system manufactured under licence.
- Tube Tech's own lance-feeding mechanism, because of its versatility, was able to accept the various diameters and lengths of lances.
- A mix of ceramic and spinning darts were also used in conjunction with Tube Tech's Rotaflex system and rotating "Soft drill".
- Tube Tech achieved the required high standard of cleaning in just 3 days, representing a time saving of 75% on methods used by other traditional contractors which normally takes up 10 days.
- With downtime running into hundreds of thousands of dollars a day, this was a vital cost-saving for the client.
- The work was carried out safely because very little high-pressure equipment were utilized, and without chemicals, no noticeable was generated.
- Tube Tech's trained confined space team used breathing apparatus to avoid inhalation of dust and vapor.